What does a building permit cost for a remodel or addition in Santa Cruz County?

A plain breakdown of the City of Santa Cruz 2026 permit fee tiers, the flat design permit fee, and what the 2025 California building code changes for your plans.

Inside the city of Santa Cruz, a remodel valued at $75,000 carries a building permit fee of about $1,770 under the citywide fee schedule effective January 1, 2026. The surprise for most homeowners is that the planning fee is often larger than the building permit fee: a design permit for a remodel or site alteration is a flat $2,536 on the planning fee schedule effective January 1, 2026.

That is why a percentage rule of thumb misleads people in both directions.

How the city calculates the building permit fee

These are the building permit tiers from the citywide fee schedule effective January 1, 2026:

  • Valuation of $1.00 to $500.00: $214.00 (citywide fee schedule)
  • Up to and including $2,000.00: $214.00 for the first $500.00 plus $7.00 for each additional $100.00 (citywide fee schedule)
  • Up to and including $25,000.00: $327.00 for the first $2,000.00 plus $14.00 for each additional $1,000.00 (citywide fee schedule)
  • Up to and including $50,000.00: $665.00 for the first $25,000.00 plus $31.00 for each additional $1,000.00 (citywide fee schedule)
  • Up to and including $100,000.00: $1,445.00 for the first $50,000.00 plus $13.00 for each additional $1,000.00 (citywide fee schedule)
  • Up to and including $500,000.00: $2,132.00 for the first $100,000.00 plus $3.00 for each additional $1,000.00 (citywide fee schedule)

Read the shape of that table before you read the numbers. The marginal rate falls to $3.00 per additional $1,000 above $100,000 of valuation (citywide fee schedule). A large addition does not pay proportionally more.

Two worked examples

A $75,000 kitchen and bath remodel sits in the band topping out at $100,000, so the arithmetic is $1,445.00 plus 25 increments of $13.00, which is about $1,770 (citywide fee schedule).

A $300,000 addition sits in the band topping out at $500,000, so it is $2,132.00 plus 200 increments of $3.00, which is about $2,732 (citywide fee schedule).

Four times the project, roughly one and a half times the building permit fee.

The planning fees that sit on top

Planning review has its own schedule. These fees do not scale down for a small project. From the planning fee schedule effective January 1, 2026:

The design permit is the one that catches people. That single flat fee can exceed the building permit fee on a modest job.

A coastal lot stacks. An addition in the coastal zone that needs a design permit can carry the building permit fee plus $2,536.00 plus $2,403.00 before a single inspection happens (planning fee schedule).

The fees that arrive after you think you are done

These are the ones that break budgets, because they are not in the first number anyone quotes:

  • Additional plan review required by revisions, changes or additions to plans: $152.00 per hour, one hour minimum (citywide fee schedule)
  • Reinspection: $152.00 per hour with a one hour minimum, and inspection outside normal business hours: $228.00 per hour with a two hour minimum (citywide fee schedule)
  • Trade permit issuance: $75.00 for electrical, $64.00 for mechanical and $64.00 for plumbing (citywide fee schedule)
  • Green building program management: 1 percent of project valuation with a $50,000 maximum (citywide fee schedule)

Reinspections are the avoidable ones. Beyond the fee, there is the schedule slip while a crew waits.

What changes with the 2025 code

The city's Building and Safety division states that all new building permit applications shall comply with the 2025 California Building Standards Codes, effective January 1, 2026, along with local amendments in Title 18 of the Santa Cruz Municipal Code (Building and Safety, City of Santa Cruz). The state Building Standards Commission published the 2025 triennial edition on July 1, 2025 with that same January 1, 2026 effective date (California Building Standards Code, Department of General Services).

Here is what that means in money. If your plans were drawn in 2025 against the prior code cycle and you submit in 2026, the drawings get reviewed against the new one. Energy, ventilation and structural details that passed under the old cycle may need updating, and the resubmittal is billed as additional plan review at $152.00 per hour (citywide fee schedule). On a set of plans that has been sitting, that is a real number, and it comes with weeks of calendar time.

If you have a finished set of drawings from last year, the first call should be to your designer to confirm the plans are current to the 2025 codes, not to the permit counter.

Outside the city limits

Everything above is the City of Santa Cruz. For a project in the unincorporated county, fees come off the County's Unified Fee Schedule through the Unified Permit Center, and the County collects building permit fees at three points in the process: at application submission, at permit issuance, and before the project is complete (Fees and Payments, County of Santa Cruz).

If your project is in Capitola, Scotts Valley or Watsonville, ask that city's building division for its current schedule. Do not assume the city of Santa Cruz numbers carry over.

For ADU permit and fee questions specifically, our guides are over at santacruzadu.com/blog.

How we handle fees on a WS project

We treat permit fees as their own line in the budget, not as a slice of a contingency. When we price a remodel or addition, we pull the current fee schedule for the jurisdiction the house sits in, identify which planning permits the scope actually triggers, and show the homeowner the building permit fee and the planning fees as separate items. Fees are a pass-through cost, so there is no reason to bury them.

We also budget hours for revision review rather than pretending the first submittal will be the last one. On the 2026 code transition in particular, we would rather spend an hour confirming a plan set is current than discover it at the plan check counter.

The practical takeaway: on a typical remodel inside the city of Santa Cruz, the building permit fee is usually the smaller half of your city costs, the flat planning permits are the bigger half, and reinspections and plan revisions are where the number moves after you sign.

Sources

  1. Building and Safety, Community Development, City of Santa Cruz
  2. Citywide fee schedule effective January 1, 2026, City of Santa Cruz
  3. Planning fee schedule effective January 1, 2026, City of Santa Cruz
  4. California Building Standards Code, Building Standards Commission, California Department of General Services
  5. Fees and Payments, Building Permits and Safety, County of Santa Cruz
  6. ADU guides for Santa Cruz County, WS Builders